To design a new $1.3M indoor pool complex and revamp an adjacent existing outdoor pool, encompassing and refurbishing the existing clubrooms to marry into the new facility.
- Total floor area of 850sq m (approx) encompassing three Myrtha pools:
- 10 x 25m lap pool.
- 10 x 4 learners’ pool.
- 3.5 x 5m toddlers’ pool with beach entrance and waterfall.
- Translucent roof over the 17m x 42m pool hall.
- Male and female changing rooms plus two family changing rooms.
- Pool-side showers.
- Office and reception areas.
- Plant room with mechanical extract system to turn air over on hot stagnant days.
LHTDesign provided full professional services including architectural, structural, lighting, filtration and treatment, and mechanical design. We also handled the contract administration.
The client Horowhenua District Council provided colour consultant and landscaping services.
During the construction process, the building contractor Colspec Construction accelerated the project completion by 62 days, which put considerable pressure on all parties involved. However despite an evolving scope, the completion deadline was successfully achieved and the residents of Foxton swarmed to enjoy the new facility.
For a client’s perspective on this project please contact Peter Shore of Horowhenua District Council Phone (06) 949 4949
|