2008 feasibility study for aquatic centre with 50m indoor pool plus other pools and hydroslides; recreation centre with 3 court stadium, fitness gymnasium etc.
Provided data and concept plans etc to Global Leisure Group and Deloitte to prepare feasibility and business plan to aquatic centre and 6 court stadium. 2008 estimate $30M.
Waikato District Council
Indoor six lane 25m deep-end pool with ramp, learners' / toddlers' pool. 1998 study estimated cost at $2M plus. Not proceeded with. Existing outdoor pool upgraded to LHTDesign specifications in 2004.
Tasman District Council
Indoor six lane 25m deep-end pool with ramp, learners' / toddlers' pool, spa pool. Study carried out in 1998. Since updated and amended for different site. Current estimate approximately $3M.
New study carried out in 2005 for aquatic centre attached to existing Events Centre with joint control. Budget $4 -$5M.
Queenstown Lakes District Council
2004 peer review and input into updated study by Strategic Leisure for a large indoor Aquatic Centre operated in conjunction with the existing Events Centre.
Central Otago District Council
Existing 25m indoor pool and learners' pool to be extended and upgraded to include a combined learners' / hydrotherapy pool and toddlers' pool plus a weights gymnasium and dry change facilities. Estimated $2.85M in 2005.
Buller District Council
2003 study for indoor six lane 25m deep-end pool with ramp, learners' / toddlers' pool and spa pool integrated with one court sports hall and weights gymnasium attached to grandstand to sports field and cycle track. Estimate approximately $5M.
Grey District Council
2003 study for indoor six lane 25m deep-end pool with ramp, learners' / toddlers' and spa pool. Estimate approximately $3.5M.
Picton Pool Group
2006 study for indoor six lane 25m deep end pool with ramp, learners’ / toddlers’ / therapeutic pool and spa pool. Estimate $4M. Comparison of four alternative sites.
2006 Initial report prepared in conjunction with Global Leisure Group for indoor swimming and indoor sports facilities. Completion of feasibility study awaiting finalization of District Council recreation strategy. |