To provide design and drawings for Building Consent and construction of tank foundations, plant room and amenities block, surround slabs, drainage and pipeline to wharf.
- Design ring foundations for three varying size tanks.
- Design surround slabs and drainage.
- Design plant room and amenities block utilising part of an existing building.
- Draw up route for wharf discharge pipeline.
- Produce as-built documentation on completion.
- Outsource Geotech report.
LHTDesign carried out the design and documentation for Building Consent and construction in three parts and co-ordinated the work with the Port of Napier who was carrying out roading and drainage works adjacent to the site at the same time.
Part 1) involved tank foundations drainage and surround slabs. Part 2) involved the plant room and amenity block. Part 3) involved drawing up the wharf pipeline.
In addition LHTDesign’s’ mechanical team were involved in the design of the hot water heating system for the tallow tanks.
The documentation was completed on time and issued for tender, Building Consent and construction.
Construction, although hindered by ground conditions and work being carried out by the Port of Napier, proceeded well with the outcome being a very smart and tidy facility.
For a client’s perspective on this project please contact Graham Klein of Whakatu Coldstores.